 |
January 2009 The kitchen is completed! Fund raising
continues for the remaining floor coverings.
|
 |
August 2008 Kent Hinson Construction begins work on the
kitchen cabinets. All appliances have been ordered and delivered.
|
 |
July 2008 John Honeycutt finished building the hangers for
the basketball goals. The drinking fountain has been installed.
|
 |
June 2008 the bathrooms have been finished by Kent Hinson
Construction and plans are underway for the kitchen.
|
 |
May 2008 Matthew Thompson begins work on finishing
trimming out windows and installing baseboards.
|
 |
January 2008 trim installation continues as well as
finishing work in the bathrooms.
|
 |
April 2007 doors and trim installation continues.
|
 |
April 2006 the sheet rocking and painting is nearing
completion.
|
 |
January 9th, 2005 the 2005 Building Fund Pledge Drive
kicked off.
|
 |
December 18th, 2004
the annual Thanksgiving/Anniversary/Christmas Dinner was held in the building
for the first time. Click to see UPDATED
PICTURES!
|
 |
November 21st, 2004 the Board hired John Splechter Construction
as Project Director for the remainder of the project.
|
 |
August 23rd, 2004 Morton Buildings
finishes assembling the shell of the building.
Click to see PICTURES!
|
 |
July 19th, 2004 Morton Buildings
work crew begins assembling the building.
Click to see PICTURES!
|
 |
July 12th, 2004 The building
materials are delivered.
Click to see PICTURES!
|
 |
May 28th, 2004 The floor and rough
plumbing are done.
|
 |
May 21st, 2004 Footings are poured
floor is next.
Click to see PICTURES!
|
 |
April 12th, 2004 Excavation Work
began.
Click
to see pictures!
|
 |
April 11th, 2004 Ground Breaking
Service.
Click to see pictures!
|
 |
March 12th, 2004 the building was
ordered and a 10% down payment was made.
|
 |
March 8th, 2004 the Board voted to
authorize the Building Committee to enter into a contract with Morton Building
to purchase the proposed building by March 12th, 2004, and to proceed with the
proposed building plan.
|
 |
March 7th, 2004 the Congregation voted to accept the proposed Morton Building
addition as recommended by the Board. Click to see PLANS!
|